How to Add Contract Dates to the Prime Contract

Copyright (c) 2023, Intercom, Inc. ( [email protected]) with Reserved Font Name "Montserrat". This Font Software is licensed under the SIL Open Font License, Version 1.1.Copyright (c) 2023, Intercom, Inc. ( [email protected]) with Reserved Font Name "Inter". This Font Software is licensed under the SIL Open Font License, Version 1.1. Table of contents Adding Contract Dates to the Prime Contract

Add custom or important dates to keep everyone on your project in the know.

Updated over 2 years ago Table of contents

Contract Dates can be added to the Prime Contract for reference. These dates can be modified at any point, even if the Prime Contract is Approved.

Locate the Contract Dates section in your Prime Contract.

Select the Edit button.

Each field from the sideblade is optional and can be left blank if the date is unknown. Select a date using the calendar icon for the following:

  • Start Date

  • Estimated Completion Date

  • Substantial Completion Date

  • Actual Completion Date

  • Signed Contract Received Date

  • Issue on Date

Start Date

Estimated Completion Date

Substantial Completion Date

Actual Completion Date

Signed Contract Received Date

Issue on Date

Select the Save button.

You have now added Contract Dates to your Prime Contract. You can modify these dates at anytime including after Approving the Prime Contract.

What's Next?

Add Attachments to the Prime Contract

Approving the Prime Contract

Related Articles Add Attachments to the Prime Contract Contracts Overview Approving a Prime Contract Add a Contract Time Limit How to Create a Prime Contract Did this answer your question?😞😐😃